A tense Chicago City Council hearing put Ballys Chicago in the spotlight.

The discussion followed the company’s slowdown on key parts of its $1.7 billion permanent casino and entertainment complex in River West. Aldermen pressed Bally’s executives on finances and job impacts. They also asked if pausing non-gaming work breaks the city’s Host Community Agreement.

Ballys representatives reiterated what they said in August: the casino floor is still on track to open in early 2027. Ironically, workers at the site recently hit a construction milestone before the slowdown occurred.

But it is important to point out that a slight delay in the building of the new casino was almost expected.

sweepstakes casino promo codes

What Slowed Down at Ballys Chicago?

Last month, Bally’s told its general contractor it was “resetting the pace” of construction.

The slowdown hit nearly all non-gaming parts of the project. That includes the roughly 34-story, 500-room hotel. It also includes a large event and concert venue. Restaurants, VIP lounges, a comedy club, and cigar rooms are affected too. So is a top-level panoramic event space.

Work on the casino gaming floor has continued. Bally’s says the initial opening for that portion still targets early 2027. Reports indicate the pause affected about 12% of the overall project. It led to layoffs of roughly 136 employees. Impacts were felt across the union trades workforce. That workforce had swelled to around 1,500 workers on site. Bally’s made its $4 million annual payment to the city on Tuesday before the hearing. The company called it a sign of commitment to the Host Community Agreement.

There may be a change coming to the way casinos in Illinois, that are not in the Chicago-area are taxed.
Bally's Casino in Chicago is temporarily located within the Medinah Temple Building in the River North neighborhood. Image Credit: Shutterstock

Why Did Bally’s Hit the Brakes?

Bally’s points to Chicago’s 2026 budget decision.

The city authorized video gambling terminals (VGTs) in bars and restaurants. The company calls this the main reason for the slowdown. Bally’s argues that “uncontrolled proliferation” of VGTs breaches the 2022 Host Community Agreement. The agreement included a commitment not to expand gaming in ways that would compete with the casino.

Executives told aldermen it would be “irresponsible” to keep investing heavily in amenities. They said they need clarity on gambling competition first. They also warned about revenue cannibalization from thousands of potential terminals across the city.

City Council approved VGTs as part of the 2026 budget. This happened over Mayor Brandon Johnson’s objections. The city budgeted modest VGT revenue of about $6.8 million. Few or no city VGT licenses had been issued by the time of the hearing. Bally’s has asked the city to reimpose restrictions on VGTs. The company warned that widespread terminal availability could cut top-line casino revenue by 30–50%. It cited what has happened elsewhere in Illinois.

Work on the casino gaming floor has continued even as non-gaming amenities were paused in August 2026.
The $1.7 billion Ballys Chicago project includes a casino floor, a 500-room hotel, and multiple entertainment venues. Image Credit: Bally's

What Did Aldermen Say at The Hearing?

The License and Consumer Protection Committee session turned tense.

Some aldermen called the dynamic a “circus.” Others said they were “stonewalled top to bottom” by both Bally’s and the mayor’s team. About 28 aldermen had earlier demanded that Bally’s resume full construction. They called for a hearing. They argued the Host Agreement requires delivery of the full complex. That means more than just the gaming floor. They also said slowing non-gaming work is a material change. They believe it should need Council approval.

Critics suggested the VGT issue is a pretext for cash-flow problems. They pointed to Bally’s debt load and recent losses. They cited an August 2026 SEC filing. It included a “going concern” statement. It noted “substantial doubt” about the company’s ability to continue without additional financing. Aldermen grilled executives on whether Bally’s can fund the remaining roughly $400 million in work. They asked how many jobs are at risk. They also asked if the company can still deliver the hotel and event center.

Bally’s representatives pushed back. Senior corporate development and legal officers spoke at the hearing. They insisted they have financing for the project. They said the slowdown is about VGT uncertainty. They denied it is about an inability to pay. They said proceeding fully without clarity would be irresponsible. Committee Chair Ald. Debra Silverstein closed the three-and-a-half-hour hearing. She promised another session with more city officials. Senior mayoral aides were invited but did not appear at this one.

list of prediction market apps with promo codes

How Does This Affect Chicago’s Budget and Pensions?

The Ballys Chicago project was sold as a major economic development engine.

Projections once included hundreds of millions of dollars in annual tax revenue. Some of that revenue was earmarked for police and firefighter pensions. The temporary casino at Medinah Temple has operated since 2023. Results have fallen short of early forecasts. That adds to concerns about the permanent resort.

City leaders worry that delays or downsizing could mean fewer visitors. They also worry about lower spending and less tax revenue than promised.

The VGT rollout was meant to bring new licensing fees and tax dollars into the 2026 budget. Little or none of that revenue had materialized by the time of the September hearing.

a rendering of the casino floor at the ballys chicago casino and hotel that is set to open next year.
Despite the delay, the casino is expected to open in 2027. Image Credit: Bally's

What’s Next for Ballys Chicago?

The dispute now sits at the intersection of contract law, city policy, and corporate finance.

Chicago officials have reminded Bally’s about its agreement. It calls for a full casino complex. Officials say disagreements over the Host Community Agreement should go through mediation. They say that is better than a construction shutdown. Bally’s is using the construction schedule as leverage. The negotiation is now high-stakes. It centers on VGT policy and the economic assumptions behind the resort.

A follow-up hearing with more city officials was indicated. The situation could still head toward legal action. It could also lead to a renegotiated set of expectations around amenities and timelines. For now, Bally’s maintains that the casino floor will open in early 2027. The hotel and many entertainment components remain paused. The company is waiting for clarity on the VGT landscape.